What Blaine Crossing's 614 Units Mean for a Hailey Home Search Before 2037

At an informal open house on the side patio of La Cabanita in Hailey, the family behind Blaine Crossing tried to correct the way people were talking about the project. "This is the very beginning of the process, and I think there's a misconception about the time frame for all of this," Andrew Oppenheimer told the 5B Gazette. "It gets lost in the conversation that the timeline goes into 2041. It's not happening overnight."

The 2041 date is the detail buyers need. Blaine Crossing is usually described by its total of 614 residential units on Flying Hat Ranch, between Hailey and Bellevue. Most of the first decade, though, is apartments. Every single-family home in the plan falls in the final phase, 2037 to 2041, and none of it can start until Hailey decides whether to annex the land. That decision isn't expected before June 2027. If you're comparing Wood River Valley towns for a single-family home, this project leaves the near-term supply you're shopping in where it is.

The order the application builds in

The phasing plan filed with the City of Hailey assigns every parcel to one of three five-year windows. Seattle-based GGLO is the design firm, and Boise-based Oppenheimer Development Corp. is the developer.

Phase Window Housing Everything else
Phase 1 2027–2031 450 apartments on two parcels, 150 and 300 200,000 sq ft of light industrial, a pump station, a park, BCRD athletic fields
Phase 2 2032–2036 50 apartments, 30 townhomes 80,000 sq ft of light industrial, 25,000 sq ft of commercial, a 100-key hotel
Phase 3 2037–2041 16 townhomes, 68 single-family homes None listed

The full plan comes to 500 apartments, 46 townhomes and 68 single-family homes. About 73 percent of all the housing, 450 of the 614 units, is in Phase 1, and every unit in Phase 1 is an apartment. Townhomes start in Phase 2. The 68 single-family homes, split across parcels of 32 and 36 homes, are in the window that ends in 2041.

The phasing pairs housing with the jobs side of the project. Phase 1 combines the apartments with 200,000 square feet of light industrial space, so the early work is apartments next to employment space. That matches how the design team presented the project to the Hailey City Council in July. According to the Idaho Mountain Express, GGLO principal Mark Sindell described the aim as a neighborhood "where the workforce of the Wood River Valley can live in the Wood River Valley."

The site layout is also set by the airport. The 5B Gazette reported that the light industrial land runs along Highway 75 instead of housing because of the Airport Overlay District, which protects airspace. The land is zoned R-5 today, which means residential parcels of five acres or more.

Phase 1 can't start until annexation is decided, and hearings run into June 2027

The phasing table starts in 2027, but the approval process sets the real calendar. Here are the steps so far and the next ones on the schedule:

  1. July 2026. The Hailey City Council voted unanimously to approve an annexation review agreement. The council found that the property owners consented, that the land borders the city, and that the area is included in Hailey's comprehensive plan. The developer agreed to pay the city $35,000 for staff and consultant review, so taxpayer money doesn't fund the studies.
  2. The application. The filed fee sheet totals $41,005.64. That includes the $35,000, $1,622.25 for development agreements, and publication and mailing charges.
  3. Required studies. Under Hailey's municipal code, an annexation application must include a traffic study, a floodplain study, an avalanche study, a wildlife study, a description of water rights and a fiscal impact analysis. Public Works Director Brian Yeager told the council the city would also look at impacts on water and sewer systems and "basically any impacts to city infrastructure."
  4. Monday, Nov. 2, 2026. The Hailey Planning and Zoning Commission held the first public hearing, an overview of the 108.8-acre annexation, at Town Center West. About 80 people attended.
  5. Monday, Dec. 7, 2026, 5:30 p.m. The next hearing covers land use and open space, also at Town Center West.
  6. Through June 2027. The Idaho Mountain Express reports that more hearings on specific parts of the proposal will run through June 2027 before the city decides on annexation.

Taken together, Phase 1's five-year window would begin in the same year the annexation decision is due, at the earliest. Any change the hearings make to the land use plan could reshape the phases that follow. Jeremy Malone, vice president for Oppenheimer Development Corp., told the Idaho Mountain Express after the first hearing that "to have a successful project we need to be aligned with the community."

Water is one of the topics the hearings will have to settle. Sindell said at the open house that the land now grows alfalfa and runs cattle, with the alfalfa using about three-quarters of the property's stacked water rights. He said the project as designed would bring use down to about one-quarter, and that a third-party study of effects on the aquifer, the Big Wood River and Silver Creek was underway, according to the 5B Gazette.

The Bellevue half of the site hasn't started its own process

The Hailey annexation covers only part of the project. The Gazette reports that the full proposal spans 227 acres split between Hailey and Bellevue, with 25 or more acres in the middle set aside for the Blaine County Recreation District. The packet describes the fields and open space as a 34.22-acre buffer between the two towns. As of the Gazette's report, the project had not started Bellevue's annexation process.

Bellevue is also in the middle of its own infrastructure work. The city's wastewater plant was out of commission and running on backup lagoons in the Idaho Mountain Express's latest report. The city was weighing a prioritized package of 18 improvements estimated at $24.813 million. BCRD Executive Director Mark Davidson has said the district's plans for the fields won't be concrete until the annexation process is resolved, according to the Mountain Express.

The project needs two cities, and each is at a different stage. Hailey has hearings scheduled into mid-2027. Bellevue had not begun its process. Blaine Crossing would be built on a sequence of steps that hasn't started yet, which makes it a long-range proposal.

What it changes, by the kind of home you're shopping for

The headline unit count means something different depending on what you're looking for:

  • Apartments. These come first. All 450 Phase 1 units are apartments, with another 50 in Phase 2.
  • Deed-restricted and locals-only housing. The developer's FAQ says it is "targeting 100 units with a combination of locals only and other deed restricted housing." Its September 16, 2026 press release places that workforce housing in "an initial phase." The 5B Gazette notes that people remain on waiting lists at housing organizations, including ARCH Community Housing Trust.
  • Townhomes. The first 30 come with Phase 2, from 2032 to 2036. The remaining 16 are in Phase 3.
  • Single-family homes. All 68 are in Phase 3, from 2037 to 2041.

For someone shopping for a single-family home in Hailey in the next few years, Blaine Crossing adds nothing to compare against. The homes for sale will be the existing ones. The project matters more as a sign of where south Hailey may be heading. Sindell described the mix to the 5B Gazette as options "for those who want to rent an apartment, buy a townhome or build a single-family home," and the phasing puts those options in that same order.

Opinion on the proposal is split. At the July council meeting, Blaine County Commissioner Lindsay Mollineaux questioned during public comment whether a project with a hotel and light industrial space fits Hailey's comprehensive plan, the Idaho Mountain Express reported. Other attendees at the open house supported the project or welcomed the proposed recreation fields, according to the Mountain Express. The plan could change before a vote, so the phasing table describes what has been filed. It may not be what gets built.

FAQ

Is Blaine Crossing approved? No. Hailey's hearings began on Nov. 2, 2026, and are expected to continue through June 2027 before the city decides on annexation.

Where can I read the application? The City of Hailey's active land use applications page links to the annexation application, the project description, the phasing plan and the supporting studies.

When is the next public hearing? Monday, Dec. 7, at 5:30 p.m. at Hailey Town Center West. It will cover land use and open space.

If you're weighing a south Hailey purchase and want to know how a long-range project like Blaine Crossing fits into pricing and timing over the years you plan to own, Jordan Jadallah can walk you through the filed plans along with current sales data for the homes you're considering. Schedule a free consultation.

Work With Jordan

Your real estate journey deserves exceptional care, and that’s exactly what Jordan Jadallah delivers. With a tailored, white-glove approach, Jordan provides every buyer and seller with personalized guidance and a seamless, stress-free experience from start to finish.

Follow Me on Instagram